Talison Tantalum Plant

Contract: Removal and Disposal of all redundant Buildings and Plant/Equipment

Duration: 9 – 12 Months

JPD are to dismantle/demolish, remove and dispose off-site all redundant miscellaneous plant/equipment, buildings, scrap and general waste from the Areas listed below.

  • Area 1 – New Mill Building
  • Area 2 – New Gravity Building
  • Area 3 – Existing Tantalum Building
  • Area 4 – End bay of Existing Tantalum Building

Consisting of but not limited to:

  • Feed hopper and conveyor located near the old flock shed
  • All Compressors, Dryers and tanks from the old Flock Shed
  • Flock shed and remaining contents
  • Pipe train bridge and contents from the water tanks to the redundant plant
  • 4 x 2000kva transformers (Talison may wish to purchase one for a spare)
  • MCC Switch rooms and contents
  • Mills switch gear from MCC south east corner of plant
  • 4 x mills and associated switch gear/transformers and spares
  • 1 conveyor system – CV 17
  • 4 x gantry cranes
  • 2 x banana screens
  • 2 x thickener tanks
  • 8 x Russell jigs
  • All spiral banks & distributors
  • All cyclones
  • All derik screens
  • All shaking tables
  • 1 x Filter belt
  • 1 x Dryer & bag house
  • 1 x Small ball mill
  • 1 x Kelsey jig
  • All Warman/Ash pumps
  • All non-ferrous and ferrous scrap materials